PROJECT |
CLIENT |
DATE |
DESCRIPTION |
STATUS |
San Remegio Project, Philippines |
Nippon Salvage Company, Ltd. / J Power Systems |
Jan 2011 |
CAPJET MAXI construction and testing. Burial depth 3m on soft, hard, mud, silt and sand mixture seabed |
Completed |
Cometa Project, Spain |
Nexans Norway AS |
Feb 2011 |
Cable PULL IN assistance support plus divers. CAPJET MAXI trenching for cable protection on sand with 1.5m trench depth. |
Completed |
Russky Project, Russia |
Nippon Salvage Company, Ltd. / J Power Systems |
Apr 2011 |
CAPJET MAXI Trenching 3m trench depth for Submarine Power Cable |
Completed |
La Reunion Project, France |
Nexans Norway AS |
May 2011 |
CAPJET MINI Trenching of submarine power cable to 1.5m trench depth. Supply of support vessel and cable laying assistance |
Completed |
Hainan Project, China |
Nexans Norway AS |
Aug 2011 |
CAPJET High /Low pressure burial depth of 1.5m hard clay. Supply of support vessel. |
Completed |
Atami Project, Japan |
Nippon Salvage Company, Ltd. |
Oct 2011 |
CAPJET MINI trenching of submarine power cable with and without armouring. Trench depth 1.5m |
Completed |
Maruyama Project, Japan |
Nippon Salvage Company, Ltd. |
Dec 2011 |
FOC Capjet with High/Low Pressure. Trenching of Fiber Optic Cable to 1.5m trench depth on 1.0m sand and 0.5m hard clay (200Kpascal) |
Completed |
Hakodate-Hokkaido Project, Japan |
Nippon Salvage Company, Ltd. |
Jun 2012 |
CAPJET MINI trenching of power cable with a trench depth of 1.5m |
Completed |
Estonia-Finland Estlink 2 |
Nexans Norway AS |
Jun 2012 |
CAPJET Trenching of Submarine Power Cable. |
Completed |
Onomichi Project, Japan |
Nippon Salvage Company, Ltd. |
Oct 2012 |
CAPJET Trenching of Submarine Power Cable to 1.5m |
Completed |
Dredging Project, Philippines |
Van Oord |
Nov 2012 |
Gather 48 sampling seabed using Vibro Core Operations and Penetration Test in a water depth of 15m. |
Completed |
Fukushima Project, Japan |
Nippon Salvage Company, Ltd. |
May 2013 |
CAPJET Trenching of Submarine Power Cable to 2m with cast iron pipes |
Completed |
Estonia-Finland Estlink 2 Additional Work |
Nexans Norway AS |
July 2013 |
CAPJET Trenching of Submarine Power Cable |
Ongoing |
MONITA Project, MontenegroItaly |
Nexans Norway AS |
June 2013 |
CAPJET Trenching of Submarine Power Cable |
Ongoing |
Skagerrak 4 Project, Denmark |
Nexans Norway AS |
July 2013 |
CAPJET Trenching of Submarine Power Cable |
Completed |
Iloilo-Guimaras , Philippines |
Nippon Salvage Company, Ltd. |
July 2013 |
CAPJET Trenching of Submarine Power Cable to 1.5m |
Ongoing |